How do construction liens work in Ontario, and what are the deadlines?

Applies in Ontario. The law on this page was checked on November 11, 2026.

Written and reviewed by Rana Muhammad Waqas Anwar. Last reviewed on November 16, 2026.

You did work on a property, or supplied materials, and you have not been paid. Or someone has registered a lien on your property, and you want to know what it means. A construction lien gives an unpaid contractor, subcontractor or supplier a claim against the property itself, but only if strict deadlines are met.

The short answer

In Ontario, a person who supplies work or materials to improve a property can have a lien on the owner's interest in it for the unpaid price. To keep the lien you must, in most cases, register a claim for lien on the property's title within 60 days. You then have 90 more days to start a court action in the Superior Court of Justice. A lien that misses either deadline expires.

Owners have duties too. An owner must hold back 10 per cent of the price as the work is done, so that there is money to answer liens.

Which example is closest to yours?

Pick the situation nearest to yours. Each example is invented, and your own facts can change the answer.

I renovated a client's home and was not paid. How long do I have to register a lien?

In most cases, 60 days. Under Ontario's Construction Act, a contractor's 60 days usually run from the day the contract was completed, unless a certificate of substantial performance was published earlier.

For example: You finished a kitchen renovation, and the homeowner still owes you $28,000. No certificate of substantial performance was published. You have 60 days from the day the contract was completed to register a claim for lien on the title to the house. If you do, you then have 90 more days, counted from the end of the 60, to start an action in the Superior Court and register a certificate of action.

Next: When do the 60 days start? and Step 1: preserve the lien

The general contractor hired me, not the owner, and has not paid me. Can I lien the property?

Yes. In Ontario, a subcontractor can have a lien on the owner's interest in the property, even with no contract with the owner.

For example: You did the electrical work on a new house for the general contractor, who owes you $18,000. Your 60 days usually run from the day you last supplied work, unless an earlier date applies. You can ask the owner and the contractor in writing for the contract details and the state of accounts, and they must answer within 21 days at most. Your lien may be limited by what the owner still owes, though the owner usually still has to answer for the 10 per cent holdback.

Next: Who can claim a lien? and When do the 60 days start?

I delivered materials to a job site and was not paid. Do I have a lien?

Usually, yes. Under Ontario's Construction Act, materials delivered to the site, or built into the improvement, can give a lien just as work can.

For example: You delivered $9,000 of lumber to a house under construction, for a framing subcontractor who has not paid you. Your 60 days usually run from your last delivery to the site, unless one of the other dates comes first. Register your claim for lien on the title to the property before then.

Next: Who can claim a lien?

Someone registered a construction lien on my house. What does it mean, and can I get it off my title?

It is a claim against your property for unpaid work or materials. In Ontario you can have it taken off title by paying money, or posting security, into court while the dispute goes on.

For example: Your contractor did not pay the plumber, who registered a $12,000 lien on your house. You can ask the court to vacate it by paying in $15,000: the $12,000 claimed, plus $3,000 (25 per cent of the claim) as security for costs. The plumber's claim then continues against the money, not against your house. If you paid your contractor no more than 90 per cent before you received written notice of the lien, your exposure is generally limited to the 10 per cent holdback.

Next: If you are the owner

My lien is under $50,000. Can I take it to Small Claims Court?

No, in Ontario a lien is enforced in an action in the Superior Court of Justice, whatever the amount. For a claim within the Small Claims limit, a judge can send the trial to a deputy judge of the Small Claims Court.

For example: You have a $15,000 lien. You start the lien action in the Superior Court. Once the defences are in, a judge can refer the trial to a Small Claims Court deputy judge. Or, if you do not need the lien, you can sue for the $15,000 as a debt in Small Claims Court.

Next: Step 3: get the case to trial and What can you sue for in Small Claims Court?

I missed the 60 days. Is there anything left?

The lien has expired, but the debt may still be owed. In Ontario, once a lien expires it is gone, so you would have to sue for the money in the ordinary way.

For example: A homeowner owes you $22,000, and your 60 days passed last month. You can still sue for the $22,000 for breach of contract. Because it is $50,000 or less, you can do that in Small Claims Court, within the usual two-year limitation period. If you were a subcontractor, and the contractor was paid for your work but kept the money, you may also have a claim for breach of the trust the Act creates over that money.

Next: Other ways to get paid and How to write and file a Small Claims Court claim

The project is for a city or the province. Can I register a lien?

Not on the property. In Ontario, a lien does not attach to the interest of the Crown or a municipality. Instead, you preserve your lien by giving a copy of your claim for lien to the right office within the same 60 days.

For example: You supplied work on a municipal community centre and were not paid. You give a copy of your claim for lien to the clerk of the municipality. Some municipalities accept it by e-mail or through a web portal, and say so on their website.

Next: Step 1: preserve the lien

The owner ended my contract before the job was done. When does my 60-day clock start?

From the termination. In Ontario, a notice of termination must be published within 7 days after a contract is terminated, and the date it is published counts as the termination date for the lien deadlines.

For example: The owner terminated your contract on May 3, and you published a notice of termination on a construction trade news website on May 6. For the lien deadlines, the contract ended on May 6, so your 60 days run from then, unless an earlier date applies. You can still dispute whether the termination was valid.

Next: When do the 60 days start?

At a glance

Question Answer
Who can claim a lien Anyone who supplies work or materials to improve a property for an owner, a contractor or a subcontractor
What it is a claim against The owner's interest in the property
Time to preserve it Usually 60 days
Time to perfect it 90 days after the last day it could have been preserved
Time to get to trial Set down for trial within 2 years after the action starts
Which court The Superior Court of Justice
What the owner must hold back 10 per cent of the price, as work is supplied
Removing a lien from title Pay into court the amount claimed, plus security for costs

On this page

What is a construction lien?

A construction lien is a claim against a property for the price of work or materials that went into improving it. It ties the debt to the property itself, so the person owed money is not left relying only on whoever hired them.

The Act calls the work an improvement. It includes:

Maintenance done only to keep a building in its normal working state is not an improvement.

The lien arises when you first supply work or materials. But it does nothing for you unless you take the steps below in time.

Official source: Construction Act, sections 1, 14 and 15

Who can claim a lien?

Who you are Can you claim a lien?
A contractor, hired directly by the owner Yes
A subcontractor, hired by the contractor or by another subcontractor Yes, against the owner's interest, even with no contract with the owner
A supplier of materials Yes, for materials delivered to the site or built into the improvement
A worker Yes, for the wages earned on the improvement
An architect, engineer or designer Often, yes. An architect's services are named in the Act, and design work can give a lien in some cases even if building never starts
Someone renting out equipment Yes. Equipment rented with an operator counts as a service, and equipment rented without one counts as materials
More detail: who counts as the owner
  • The owner is anyone with an interest in the property at whose request the improvement is made, and on whose credit or behalf, with whose consent, or for whose direct benefit it is made. A tenant who orders work can be an owner.
  • A person buying a home is not treated as its owner if:
    • no more than 30 per cent of the price is paid before the home is transferred, not counting money held in trust under the Condominium Act, 1998, and
    • the home is not transferred until it is ready to live in. For a new home, that is shown by a municipal occupancy permit or a certificate of completion and possession under the Ontario New Home Warranties Plan Act.
  • A lien does not attach to land of the Crown or a municipality. See the example for public projects.

What can a lien cover?

A lien covers A lien does not cover
The price agreed for the work or materials you supplied Interest on what you are owed. You can still claim interest in the lawsuit
If no price was agreed, their market value Indirect losses, such as lost profit, lost productivity or head office overhead
Direct costs of a job that ran long for reasons you were not responsible for, such as extra equipment rental or insurance Work or materials you have not yet supplied

Do not inflate a lien. Registering a lien can make you liable for the damage it causes. That happens if you know, or ought to know, that you have no lien, or that its amount has been wilfully exaggerated.

More detail: a lien can be smaller than what you are owed

A lien is limited to what is owing to you. It is also limited by what is owed further up the chain: between the owner and the contractor, or between the contractor and the subcontractor who hired you. The holdback rules set a floor under that limit, as explained under If you are the owner.

Official source: Construction Act, sections 1, 14, 17 and 35

What are the deadlines?

Step Deadline What you have to do
Preserve the lien Usually 60 days Register a claim for lien on the property's title, or give it to the owner where the lien does not attach to the land
Perfect the lien 90 days after the last day you could have preserved it Start an action in the Superior Court, and register a certificate of action on title
Serve the statement of claim 90 days after it is issued Serve it on the defendants. The court can give more time
Get to trial 2 years after the action that perfected the lien was started Have the action set down for trial, or get an order for its trial

A lien that is not preserved, perfected or set down for trial in time expires.

These are the deadlines for contracts made on or after July 1, 2018. See Contracts made before July 1, 2018.

When do the 60 days start?

It depends on whether you dealt directly with the owner.

If you are the contractor, the 60 days run from the earlier of:

If you are anyone else, such as a subcontractor, a supplier or a worker, the 60 days run from the earliest of:

When dates compete, the earlier one counts. The clock is set by these events, not by the date of your last invoice.

More detail: substantial performance, and when a job counts as finished
  • Substantial performance. A contract is substantially performed when:
    • the improvement, or a substantial part of it, is ready for use or being used, and
    • the rest can be finished or fixed for no more than 3 per cent of the first $1,000,000 of the contract price, 2 per cent of the next $1,000,000, and 1 per cent of the balance.
  • The certificate has no effect until it is published. It is published on a construction trade news website: the Daily Commercial News, Link2Build or Ontario Construction News.
  • Small finishing work does not restart the clock. A contract counts as completed, and work as last supplied, once what remains would cost no more than 1 per cent of the contract price or $5,000, whichever is less.
  • You can ask when it was published. On written request, the contractor must confirm in writing the date and place the certificate was published.
More detail: if the contract was terminated

Within 7 days after a contract is terminated, the owner, the contractor or another person whose lien could expire must publish a notice of termination on a construction trade news website. Once a notice is published, the date of publication counts as the termination date for the lien deadlines. If more than one notice is published, the first counts. Publishing a notice does not stop anyone from disputing whether the termination was valid.

More detail: an example with dates

Say a subcontractor last supplied work on Monday, March 1, 2027, and no certificate was published and no other date came first.

  • Day 60 is Friday, April 30, 2027. The claim for lien must be registered by then.
  • Day 90 after that is Thursday, July 29, 2027. The action must be started, and the certificate of action registered, by then.
  • Two years after the action starts, it must have been set down for trial.

Count the days for your own dates, and do not leave it to the last day.

Official source: Construction Act, sections 2, 31, 32 and 39, and O. Reg. 304/18, which names the websites

Step 1: preserve the lien

You preserve a lien by registering a claim for lien, Form 12, on the title to the property at the land registry office. The claim must set out:

Construction lien documents are registered electronically. Land registry offices stopped accepting paper ones on October 11, 2016, apart from cases too large for the electronic system. Most people have a lawyer, or a firm that registers documents, do this for them.

If the lien does not attach to the land, as on a Crown, municipal or railway project, you give a copy of the claim for lien instead. It goes to the office the regulations name for the Crown, to the clerk of the municipality, or to an office of the railway in Ontario.

More detail: condominium common elements

If your lien relates to work on the common elements of a condominium, you must also give notice that you have preserved it. The notice, in the prescribed form, goes to the condominium corporation and to each unit owner.

Official sources: Construction Act forms, where Form 12 is the claim for lien, and land registration bulletin 2016-04 on electronic registration

Step 2: perfect the lien

A preserved lien expires unless you perfect it within 90 days after the last day on which it could have been preserved. To perfect it you:

  1. start an action to enforce the lien in the Superior Court of Justice, with a statement of claim issued at a court office in the county where the property is, and
  2. register a certificate of action, Form 14, on the title to the property.

Where the lien does not attach to the land, starting the action is enough.

A lien action follows its own procedure under the Construction Act. The ordinary court rules apply only where they are consistent with it.

More detail: sheltering under another claimant's action

If another lien claimant on the same project has already perfected their lien, or perfects it before yours would expire, your preserved lien can be perfected by sheltering under their action. A sheltered lien is perfected only against the defendants, and for the kind of relief, named in that action. Relying on someone else's action is risky, so get advice before you do.

Next on this site: Drafting a statement of claim for the Superior Court

Official source: O. Reg. 302/18, the procedure for lien actions

Step 3: get the case to trial

A lien action is meant to be summary, so its rules keep the steps few.

A smaller lien can be tried by a Small Claims Court judge. The Small Claims limit is now $50,000. If the action is for an amount within it, a judge can refer the trial to a deputy judge of the Small Claims Court, or to the Small Claims Court Administrative Judge.

Next on this site: What can you sue for in Small Claims Court?

Official source: O. Reg. 302/18, and the Construction Act, sections 37, 50 and 58

If you are the owner

Hold back 10 per cent. Everyone who pays on a contract or subcontract where a lien can arise must keep back 10 per cent of the price of the work and materials as they are supplied. This is the holdback. It applies whatever the contract says about payment, and stays in place until the liens that could be claimed against it have expired or been dealt with.

Paying up to 90 per cent is safe, unless you have notice. You can safely pay up to 90 per cent of the price of what has been supplied. That changes if, before paying, you received written notice of a lien. A copy of a registered claim for lien counts as written notice.

Your liability is generally limited to the holdback. If your contractor fails to pay a subcontractor or supplier, your personal liability to them generally does not exceed the holdback you were required to keep.

Release the holdback each year. Since January 1, 2026, owners must release holdback once a year:

  1. Within 14 days after each anniversary of the date the contract was made, publish a notice of annual release of holdback, Form 6, on a construction trade news website, giving the amount and the payment date.
  2. Between 60 and 74 days after publishing it, pay the contractor the holdback built up for that year, unless a lien has been preserved or perfected and is still outstanding.
  3. The contractor then has 14 days to pay each subcontractor its share, and each subcontractor has 14 days to pay the next.

For a contract made before January 1, 2026, the first annual release comes on the second anniversary of the contract after that date, and it must include all holdback built up before then.

Getting a lien off your title. The court will vacate a registered lien if you pay money into court, or post security. The amount is the full amount claimed, plus the lesser of $250,000 and 25 per cent of that amount, as security for costs. The lien then becomes a claim against the money instead of against your property. You can also ask the court to set a lower amount that it considers reasonable.

More detail: proposed changes

In October 2026, Ontario introduced a bill, the Building Ontario Faster Act, 2026 (Bill 140), that would change the dates for the yearly release. Some owners, to be named in a regulation, could pick their own yearly date: in a new contract, or by publishing a notice for an existing one. That date would replace the contract's anniversary. On November 2, 2026, the bill was sent to a committee of the Legislature. A bill is not law until it is passed and in force. Check the current Act before relying on the dates above.

Before you hire a contractor: Your rights when starting home renovations or repairs (Government of Ontario) explains written contracts and deposits.

Official source: Construction Act, sections 1, 22 to 26, 44 and 87.4

Other ways to get paid

A lien is not the only tool, and sometimes not the best one.

Route What it is Time limit
Prompt payment On contracts made since October 1, 2019, an owner must pay a proper invoice within 28 days, unless within 14 days it gives a notice of non-payment saying what it disputes and why 28 days for the owner to pay
Adjudication A quick decision by an adjudicator on a dispute, often while the job is still going on Notice within 90 days after the contract is completed, abandoned or terminated, unless the parties agree otherwise
A trust claim Money a contractor receives, or is owed, for a project is held in trust for the subcontractors and suppliers it owes. Using it for something else breaks the trust Usually two years: the Act sets no special limit, so the general rule applies. See limitation periods
Suing for the debt A claim for breach of contract, with no lien. For $50,000 or less, in Small Claims Court Usually two years

Prompt payment and adjudication apply only to contracts made on or after October 1, 2019. They do not apply to a contract made later if the owner began the procurement before that day, or to a subcontract under one of these older contracts.

Next on this site: How to write and file a Small Claims Court claim and limitation periods

Official source: ODACC, which runs construction adjudications in Ontario

Contracts made before July 1, 2018

If the contract was made, or the owner's procurement began, before July 1, 2018, the Act as it read on June 29, 2018 still applies to the project, including to subcontracts made later. Its deadlines are shorter: 45 days, not 60 and 90. If your project began before July 1, 2018, get advice on which rules apply.

What mistakes cause the most trouble?

What does the law itself say?

On who has a lien. Section 14 of the Construction Act says:

"A person who supplies services or materials to an improvement for an owner, contractor or subcontractor, has a lien upon the interest of the owner in the premises improved for the price of those services or materials."

On perfecting it in time. Section 36 says:

"A lien that has been preserved expires unless it is perfected prior to the end of the 90-day period next following the last day, under section 31, on which the lien could have been preserved."

On where it is enforced. Section 50 says:

"A lien claim is enforceable in an action in the Superior Court of Justice."

When should you get help?

Get legal advice early with a construction lien. The deadlines are short, the steps are technical, and an expired lien is gone. Advice is especially worth it when:

Next on this site: Getting legal help

Sources

The 10 sources this page relies on

Laws and regulations

Bills

Government and court guides

Forms

What changed

  • January 1, 2026. Owners must release holdback once a year, on a schedule tied to each contract's anniversary. A published notice of termination now fixes the date a contract ends for the lien deadlines. (Construction Act as amended by S.O. 2024, c. 20, Sched. 4, and by the Fighting Delays, Building Faster Act, 2025, Sched. 2)
  • July 1, 2018. For contracts made from this date, the lien deadlines became 60 days to preserve and 90 days to perfect. (Construction Act, s. 87.3)

Common questions

How long do I have to register a construction lien in Ontario?
In most cases, 60 days. They start from an event such as the day you last supplied work or materials, or the day the contract was completed, depending on your role.

Can a subcontractor put a lien on a house?
Yes. A subcontractor can have a lien on the owner's interest in the property, even with no contract with the owner. The owner's own liability is generally limited to the 10 per cent holdback.

Can I enforce a construction lien in Small Claims Court?
No. A lien is enforced in the Superior Court of Justice. If the claim is for $50,000 or less, a judge can send the trial to a deputy judge of the Small Claims Court.

What happens if I miss the lien deadline?
The lien expires. You may still be able to sue for the money as a debt, within the usual two-year limitation period.

How does a homeowner get a lien removed?
By paying into court, or posting security for, the amount claimed plus the lesser of $250,000 and 25 per cent of it. The lien then becomes a claim against that money instead of the property.

How much does an owner have to hold back?
10 per cent of the price of the work and materials as they are supplied. Since January 1, 2026, holdback must be released once a year, on a schedule tied to the contract's anniversary.

Can a lien include interest?
No. A lien cannot include interest, but you can still claim interest in the lawsuit.

Every situation turns on its own facts. Before you act, get advice on yours — speak with an Ontario lawyer or a community legal clinic.

This article is general legal information about Ontario law, current as of November 11, 2026. It is not legal advice, and reading it does not create a lawyer-client relationship. The law changes, and every situation depends on its own facts. Before acting, get advice about your specific circumstances from a lawyer or licensed paralegal — the Law Society of Ontario's Referral Service can connect you with one, and Steps to Justice offers free plain-language legal information.